Supporting Our Teachers, Supporting Our Future

For the second year in a row, MSD is proud to support one of the most important groups in our community—our teachers. This year, we were thrilled to help clear nearly all of the classroom wishlist for Mrs. Marlowe, a dedicated local teacher who also happens to be married to one of our very own team members.

Teachers play a powerful role in shaping the future, and Mrs. Marlowe is no exception. Day after day, she pours her energy, creativity, and care into guiding her students and helping them grow into tomorrow’s leaders. By helping fulfill her classroom wishlist, we hope to make her work just a little easier—and to show our appreciation for all she does.

It is truly special when we can support one of our extended MSD family members in such a meaningful way.

As a company, we believe strongly in giving back to the communities where we live and work. Supporting local schools and teachers isn’t just about supplies—it’s about investing in the future and showing gratitude for those who dedicate their lives to teaching.

With the new school year underway, we wish Mrs. Marlowe the very best. We can’t wait to see the amazing things she’ll do with her students this year, and we hope to continue this tradition of giving back to teachers for many years to come.

Mrs. Marlowe—we appreciate you!

WPAFB Sensors Lab

Wright-Patt Air Force Base sought contractors to renovate and add onto the Sensors Lab. The HVAC portion of the project was over $13 million.

  • MSD served as the Design Assist Contractor in conjunction with Heapy Engineering for this project. In collaborating with General Contractor, Butt Construction, MSD provided Design Assist solutions for the following:
    • A large, anechoic chamber
    • An outdoor range
    • Multiple, Class-100 clean rooms
    • A three-story office building addition with DCID 6-9 requirements on many of the rooms

WPAFB Chilled Water System

The chilled water system at a high-security building on the Air Force Base was undersized and unable to keep up with demand. The facility could not operate without chilled water due to the amount of information servers in the building, and the general nature of the building itself. The entire upgrade project would need to be completed with minimal shut down time at the building. HVAC portion of this project was over $3 million.

  • MSD worked in collaboration with Diaz Construction to complete the system upgrades on time and on budget with minimal shutdowns or disruption to the facility operations.

LJB, Inc.

LJB, Inc. was renovating their Miamisburg, OH office and wanted to incorporate energy-saving upgrades.

  • MSD provided Design Build services in tandem with Greensleeves Energy Solutions, a specialist in geothermal systems.
  • MSD and Greensleeves installed a new geothermal HVAC system with open and closed loops. In addition, MSD design and installed the plumbing portion of the renovation.